Mammoet has successfully completed the safe transport and installation of four 1180-ton NGL bullet tanks for Oman’s biggest petrochemical project, Liwa Plastics Industries Complex (LPIC) project which is owned by Orpic.
The bullets, each measuring 60 meters in length and 7.8 meters in diameter, were positioned on sand beds in a synchronized tandem lift utilizing a 1600-ton PTC ring crane and a 1200-ton crawler crane.
The small footprint enabled the PTC 35 DS crane to work within the limited area onsite utilizing the available space as efficiently as possible.
Mammoet has been providing ongoing heavy lifting and transport solutions for this petrochemical project since 2017 and contributed to the outstanding safety milestone of 10 million man-hours worked lost time injury (LTI) free.
Andrew Lees, SHEQ Director Mammoet Middle East and Africa, said “The achieved safety milestone is a testament to the incredible team that has been put together by our valued client. Commitment to safety is a core value and an integral part of Mammoet's culture. With every workforce member staying focused on incident-free operations we can send everyone home safely to their families each day.”