London’s largest crane rises above Earls Court

Share :

18 Likes, 3084 Views

London’s largest heavy lift crane is set to swing into action on the vast Earls Court residential redevelopment.

The 4,300 tonne AL.SK190 heavy lift crane is now fully rigged, tested and ready to begin work on site at Earls Court in London.

The AL.SK190 will lift and remove 61 portal beams from over the London Underground lines that lie below the former exhibition centre. The large concrete beams which supported the exhibition centre were installed when the centre was erected in the 1930s and need to be removed to enable a major new development on the site. The smallest beam weighs 80 tonnes while the largest is 1,500 tonnes.

Watch the Video : "ALE AL.SK190 (application example)"

Enabling works contractor Keltbray has called upon lifting technology used in the offshore industry to lift 61 portal beams out from over the London Underground lines that supported the former exhibition centres.

The largest of the Exhibition Hall supporting beams weighs in at 1,500 tonnes, the same as 118 London buses, and has been nicknamed Big Bertha.

Designed and manufactured by specialist engineering firm ALE, the 120m tall heavy lifting crane will slash nearly two years from the projected enabling works programme.

 At twice the height of Nelson’s Column, it is the largest capacity lifting crane ever to be used in London and will operate only on the Earls Court site avoiding oversail of the nearby properties.

News Image

The Earls Court redevelopment, led by developer Capital & Counties Properties, will create 8,000 homes and 10,000 new jobs as well as a new High Street and a new five-acre park in London.

Kelbray has completed demolition of the former exhibition centres to ground level after two years of intensive work on site.

David Rowe, technical manager for Keltbray at Earls Court said: “By utilising this crane and lifting method, disruption is minimised and the crane’s high capacity and precision lifting technology will reduce the overall project timescale considerably.

“The lifting of the large portal beams is the next big task at Earls Court as we prepare the site for construction.”

The first lifts will take place later this month.

Removal of portal beams will occur overnight in ‘engineering hours’ after the last District Line train has passed through the tunnels underneath the beams.

Work is expected to conclude by the end of 2017 when the crane will be dismantled and leave Earls Court.

Giovanni Alders, Sales Manager, Global Projects Division for ALE said: “Operationally, this crane can perform lifts previously unachievable and reinforces the innovation seen throughout the whole project. We are looking forward to progressing with the project and executing the first lift.”

Credits : www.constructionenquirer.com

News Image

Share :

18 Likes, 3084 Views

Latest Cranes
Similar News